Chinehwa has been awarded the change order from Alstom on Nov. 16, 2012 to increase quantity of the ducts for Tanjung Bin project. The added ducts are around 920mt for 8 groups. The total quantity for Tanjun Bin now is around 1520mt.
According to the contract and erection schedule at jobsite, the added ducts will be delivered from March next year.